Our Ironbridge House development of 57 beautifully designed apartments in the vibrant Hanwell area of West London has progressed rapidly since its acquisition in June 2020.

As you can see from the photos the new build block is now constructed and scaffolding has been struck on all elevations revealing the true beauty of this iconic building’s transformation.

The fit phases are well underway, and a detailed review of progress to-date is below. The incoming utility services are all scheduled and preparation almost complete to start receiving final connections.

In the phots you will also see images of the existing building and the CGI’s (computer generated images of what we envisaged the outcome to be. We think you will agree the results are incredibly accurate and we should all be proud of the part we have played in this development, including you as a much-valued investor. Thank you!

Extension Block (new build)

    • Level 4
      • Party wall track installed wall construction commencing 20th Oct
    • Level 3
      • Party and internal walls installed
      • Mech 1st fix complete
      • Electrical 1 1st complete
      • Walls and ceiling closed
        • Tape and joint complete
        • Mis coat complete
      • Bathrooms being tiled (completion 23/10)
      • Kitchens being installed (completion 29/10)
    • Level 2
      • Party and internal walls installed
      • Mech 1st fix complete
      • Electrical 1st complete
      • Walls and ceiling being closed W/C 25/10
        • Tape and joint commences 1/11
        • Mist coat commences 4/11
      • Bathrooms being tiled commences 6/11
    • Level 1
      • Party and internal walls installed
      • Mech 1st fix complete
      • Electrical 1st fix complete (22nd Oct)
    • Ground
      • Screed floor installation to commence 15th Nov
  • Tower Block (Conversion)
    • Party walls installed by 29th Oct
    • Acoustic batons and T&G flooring to commence 25 Oct (duration 2 weeks) for levels 2,3,4,5,6 and screed board on L1
  • External
    • Service trench dug and utilities to commence installation w/c 25th Oct

Tower block Practical Completion June 2022

Extension block Practical Completion July 2022